Forrester in Mernda

Our project in Mernda with Burbank

Carpet installed

I have just checked Burbank’s My Place and found that the carpet has been as completed. This means that the last thing inside the house been completed five months after starting and the remaining things will be on the outside. I will have some photos after the weekend visit but for now this is “My Place” extract:

Carpet

Carpet completed

Stormwater and drainage completed

Another stage has been completed with stormwater and drainage completed.

I think so far things have been well and stages being completed when stated. The next stage for completition will be the slab.

stormwater

stormwater

drainage

drainage

Earthworks completed

Its a been while that there has an update in My Place but today there is an update and the earthworks have been completed.

This has transformed the site into a neat flat block of land. Also earthworks were done for our neighbour today.

earthworks

earthworks

According to My Place the next stage is Set out.

Finance approved

With Burbank now having come back from the Christmas break, there has been an update in My Place.

The update shows that the financing has been approved.

financeapproval

Finance approval

Clean up time

Construction should be starting either at the end of the month or in February and so its better to clear the growing bushes a bit.

Our block of land has so much weeds and the ones near don’t seem to have that much. Maybe its very fertile soil!

bushy growth

Clean up time

Building permit given

I have checked in Burbank’s My Place and have seen that before Burbank closed for the holidays, they managed to get the Building Permit.

Building permits are the documents that signify that a building surveyor has approved documentation for the proposed building work before the construction of that building starts.

This is a good thing and now there is only three steps left to be completed: Client approves drawings, Finance approval and site start letter sent.

The finance approval will be ready by the time Burbank re-opens and then they should sent us the final drawings.

building permit

My Place update

Engineering completed

 

I logged on to My Place and saw that Engineering is now completed.

 

Engineering

The next phase is now Contract signing. We wont be available to do that until week commencing 19th December.

Burbank will close on Thursday 23rd of December and so we will have four days.