Forrester in Mernda

Our project in Mernda with Burbank

Slab preps taking place

The preparations for the pouring of the slab are continuing with materials being delivered.

It looks like everything has been delivered so far and slab could be poured in the next two days or so:

steel

pods

preps

Stormwater and drainage completed

Another stage has been completed with stormwater and drainage completed.

I think so far things have been well and stages being completed when stated. The next stage for completition will be the slab.

stormwater

stormwater

drainage

drainage

Earthworks completed

Its a been while that there has an update in My Place but today there is an update and the earthworks have been completed.

This has transformed the site into a neat flat block of land. Also earthworks were done for our neighbour today.

earthworks

earthworks

According to My Place the next stage is Set out.

Construction about to start

Finally the actual construction will be starting soon because now we have signed and returned the final drawings.

There have been some delays were never anticipated but its good that now our file will be moving to construction and that should be a more interesting phase.

Hopefully there will be more frequent posts.

Here is the Burbank sign that we have now put on the block:

Burbank sign

Burbank sign

Update: when we came back after two days the sign was missing. Interesting.

Concrete block on the land

Today were surprised to fine that a concrete block has been dumped on our block of land.

Our land is near a substation and what has happened is there were some repairs that needed for a footpath block to be removed.

The people working on the sub then decided to dump the footpath concrete block. Its very heavy and not something that one can just move.

concrete block

Concrete block

broken footpath

Broken footpath